Progress Billing for Contractors: Schedule of Values & Retainage Guide
Progress billing is the standard invoicing methodology for multi-month construction, commercial engineering, and large renovation projects. Rather than waiting for a job to conclude to submit a massive bill, contractors invoice incrementally based on verified percentage-of-completion milestones.#
1. How a Schedule of Values (SOV) Works
Before breaking ground, the general contractor and project owner establish a Schedule of Values—an itemized matrix dividing the total contract into distinct trade phases: - Phase 1: Site clearing and foundation ($25,000) - Phase 2: Structural framing and trusses ($45,000) - Phase 3: Plumbing, electrical, and HVAC rough-ins ($38,000) - Phase 4: Insulation and drywall ($22,000) - Phase 5: Interior trim, paint, and fixtures ($30,000)#